AMATS: Rabbit Creek Road Rehabilitation

Schedule

The following identifies key project milestones. Dates are subject to change based on project needs, funding availability, and stakeholder input. 

TASK ANTICIPATED COMPLETION
Public Involvement Ongoing
Preliminary Engineering and Environmental Documentation Spring 2026 - Summer 2027
Final Design Summer 2027- Summer 2030
Right-of-Way Acquisition and Utility Coordination Winter 2029 - Summer 2031
Construction 2031*

*Contingent on funding